Hemlock Creek Watershed Utility Improvement Project Update

2/11/2019

*** Hemlock Creek Watershed Utility Improvement Project ***

BRIEF PROJECT UPDATE REGARDING COMPLETED ITEMS

As of the week of February 11, 2019, the following items have been completed on the Project:

HILLSIDE ROAD: Sanitary sewer mainline and laterals installed from H.N.’s 2461 to 1549; Work suspended; anticipated for completion in April 2019
OAK LANE: Sanitary sewer mainline, laterals, and new water main installed; Water main needs connecting to Hillside Road; Storm sewers to be performed
SHADY LANE: Sanitary sewer mainline, laterals and new water main installed; Storm sewer point repairs complete and water main completed. 
SEVEN HILLS BLVD.: Sanitary sewer mainline and laterals installed from Starlight Drive to Cherry Lane.
TWILIGHT DRIVE: Sanitary sewer mainline and laterals installed; Storm sewer point repairs completed; Culvert pipe repairs in progress.
MARY LANE: Sanitary sewer mainline installed
NORTH MARY LANE: Sanitary sewer mainline installed
SOUTH MARY LANE: Sanitary mainline in progress
NEMET DRIVE: Sanitary sewer mainline installation and storm sewer point repairs are in progress
CHERRY LANE: Work has not started as of this update

Feel free to check back for additional Project updates.

Thank you for your continued patience throughout the construction process.